MAIN BUILDING

 

TRAINING CENTER

46,000 square feet: dorms, classrooms, common rooms, recreation facilities   61,000 square feet
›  North wing basement, first floor north and south dorm wings complete, with floor slab, walls and ceilings.
›  Second floor load bearing masonry walls going up.
›  Center block structural steel in place.
›  Stone on exterior lower level started.
 
›  Foundation completed; lower level slab and walls complete.
›  Structural steel and floor decking in for office/classroom area.

To follow the progress of the new BAC/IMI National Training Center project, go to: http://www.imiweb.org/_whatsnew/index.php.

 

 

620 F Street NW
Washington, DC 20004
Phone: 202.783.3788
Toll free: 1.888.880.8222
Email: askbac@bacweb.org

CANADA - IMI - IPF -IHF